East Tsing Yi Viaduct

The East Tsing Yi Viaduct connects the Stonecutters Bridge and Nam Wan Tunnel. This viaduct, which is a dual three-lane viaduct, forms part of the 7.6 km long Route 8 that links Lantau Island, Tsing Yi Island, Cheung Sha Wan Island, and Sha Tin. 

Within the scope of the contract, BYME was tasked to provide the Electrical, Fire Services and Plumbing & Drainage System for road traffic and other services.

Client

Highways Department

Construction period

Dec 2004 – Feb 2008

Scope of works

  • Power supply and distribution systems for road gantry equipment
  • Lighting & small power system inside viaduct service tunnel
  • Earthing & Lightning Protection Systems for viaduct
  • Fire Services System at viaduct centralized FS pump room
  • Plumbing & Drainage